Role : Project Manager.

From Real Estate Only.

- Experience from Residential HIgh rise building.

Objective of the Role:

- Responsible to execute & monitor work.

- Ensures quality standards are met.

- Ensures Labor & material are well planned.

Skills & Experties:

- Managerial skills: Planning, monitoring and scheduling work.

- Technical Expert.

- Expert in construction management.

Key Responsibilities:

I) Independent charge of the Project under the guidance of Zonal Manager & control of the management for a new Project:.

(i) To cross-check the actual boundaries with City Survey/demarcation / Architects layout.

(ii) To locate encroachment, roads, trespassers' paths, trees, electric & other poles, existing structures, drainage/water supply line passing through, nalla, culverts, etc.

(iii) To locate main drainage lines & water supply line for feasibility of the connections of the project in future.

(iv) To clean the plot.

II) Authorities for input submission through Zonal:.

a) The Director.

b) Architect/Structural / MEP Consultant for finalizing the drawings.

III) Check points in Preliminary drawings.

a) The out/out dimensions of plot boundaries.

b) Setbacks.

c) Orientation of proposed buildings.

d) Center line drawings.

e) Finalization of plinth levels of various proposed structures.

IV) Infrastructure set up to start new project.

(i) Fencing/boundary wall.

(ii) Approach Road to the project.

(iii) Site office & store.

(iv) Material Stacking yard.

(v) Water storage & electrical connection.

(vi) Security arrangements.

(vii) Streetlights.

(viii) Labour camp.

VI) Preparing a Bar Chart as per priorities & commitment in brochures & get it approved, from the management through the Zonal manager.

VII) Required approvals before proceeding for actual works at site.

(i) Setting out of building/buildings.

(ii) Respective plinth levels.

(iii) The bar chart from the Director.

VIII) Project Manager shall confirm:.

(i) Final centreline drawings.

(ii) RCC drawings.

(iii) Trial pits, for finalization of type of foundation.

IX) Project Manager shall get introduced to the contractor/ contractors selected by the management for every item and shall judge his capacity & capability in regards to quality & timely completion of work.

X) To give regular feedback about the manpower, material, tools and plants, machinery, etc.

to the management.

XI) He should control all the activities at site in association with the project team and control & guide them in terms of quality, time & material management.

XII) In consultation with the Zonal Manager, he shall distribute the work reasonably to the Project team.

XIII) He shall avail training to the site staff for proper execution & supervision at site.